PROGRAMME OF COMPLETION:
Tentatively, Phase-1 of the project is
programmed for completion in the financial year 2014-2015.
APPROVAL OF GOVERNMENT OF INDIA:
The Government of Tamil Nadu have approved
in principle the two initial corridors on 7-11-2007. The
Government of India have approved the Chennai Metro Rail project on 28-1-2009.
SIGNING OF LOAN AGREEMENT WITH GOVERNMENT OF JAPAN:
The estimated base cost of this project is about Rs.14000 crores, Of
this, the Central and State Governments together are expected to
contribute about 41%. The balance will be met by a loan granted by
the Japan International Cooperation Agency (JICA).
JICA has since agreed to finance the project and the loan agreement
between the Government of India and the Government of Japan was
signed on 21-11-2008 at Tokyo.
APPOINTMENT OF GENERAL CONSULTANTS:
Chennai Metro Rail Limited has appointed the
"General Consultants" (GC)
for
Phase-1 of the project on 24.02.2009. A five member consortium led
by Egis Rail S.A., France have been appointed as General
Consultants. The other members of the consortium are (a) Egis India
Consulting Engineers Private Ltd., India, (b) Maunsell
Consultants Asia Ltd., Hong Kong, (c) Balaji Rail Road Systems
Ltd., India & (d) Yachiyo Engineering Co. Ltd., Japan. The General
Consultants will assist Chennai Metro Rail Limited in design,
supervision, quality control, safety and contract management for the
project.
AWARD OF TENDERS:
Details of tenders
awarded are given at the link "tenders" provided on top left side of
this page.
PRIME
CONSULTANT:
Chennai
Metro Rail Limited (CMRL) has appointed Delhi Metro Rail Corporation
(DMRC) as the Prime Consultant (PC) for Phase-1 of the project. The
Prime Consultant will assist CMRL in an advisory role in the
execution of the project.
|